Electrical gear substitution
The specified gear carries a lead time that no longer supports the current sequence, and a substitution has been submitted for review. Pricing has been received but scope and warranty terms are still being evaluated, so the amount remains pending exposure rather than approved cost. The required decision date has passed, which is tracked separately from the workflow status.
- Source
- Procurement
- Responsible party
- MEP / Electrical
- Identified / decision due
- Mar 11 / Mar 18
- Days open
- 9
- Estimated cost
- $44,000
- Submitted cost
- $48,000
- Approved cost
- —
- Pending exposure
- $48,000
- Forecast impact
- Forecast updated for potential exposure
- Schedule impact
- Equipment release at risk
- Affected activity
- Switchgear release / electrical rough-in
- Related records
- Procurement package · Submittal: switchgear (in review)
- Decision / notes
- Awaiting review of submitted pricing and equipment substitution backup. No approval has been issued.