Two- or three-week construction lookahead

Copy activities from the approved schedule; this daily planning grid does not calculate dependencies, float or a critical path. Use 14 columns for a two-week window, or all 21 for three weeks. Fill the calendar-date row first; mark work only after the team reviews constraints.

Edit highlighted paragraphs and table cells directly. Save edited HTML to keep your work; this page does not send or save data automatically.

Window and source

Project / start / horizon / schedule revision

[Project] / [YYYY-MM-DD] / [14 or 21 days] / [approved schedule ID]

Weekly review

Name the superintendent and trade participants. At each weekly review, record completed work, carry forward unfinished tasks and add the next week. Do not silently move the baseline.

Daily work grid

Activity / locationTrade / crewOwnerDay 1Day 2Day 3Day 4Day 5Day 6Day 7Day 8Day 9Day 10Day 11Day 12Day 13Day 14Day 15Day 16Day 17Day 18Day 19Day 20Day 21Row action
Calendar dates[date][date][date][date][date][date][date][date][date][date][date][date][date][date][date][date][date][date][date][date][date]
Fictional: level 2 ceiling inspectionInspection coordination[name]Inspect
[activity/location][trade/crew][owner]

Constraint and readiness log

ActivityPredecessor / release evidenceLaborMaterialsAccess / permit / designConstraint ownerRequired byReady?DecisionRow action
Level 2 ceiling inspectionAbove-ceiling review record pendingInspector confirmation pendingN/AAccess escort pending[name][date]NoConfirm evidence before promising inspection date
[activity][record][availability][delivery][constraint][owner][date][yes/no][action]

Save edited HTML to keep an editable local copy, including added rows. Reopen that HTML file in a browser to continue. Print or Save as PDF produces a static handoff copy; it does not retain editable fields. This is an HTML worksheet, not an XLSX workbook.